Understanding the process
A brief guide to help manage expectations for a stress free transaction.
Production, Scheduling & Installation
Batch Manufacturing Model
Doors, windows and staircases are produced in many cases using a batch manufacturing process.
This allows consistent quality, efficient use of materials, and realistic pricing.
Many components are prepared in standardised stages and only trimmed and adjusted at later phases to ensure a precise bespoke fit.
Because of this workflow, projects are not manufactured start-to-finish individually.
Project Phases
Each order progresses through the following stages:
Booking
Order of materials
Manufacturing (milling, cut lists, jointing, etc)
Glass ordering (if applicable)
Finishing
Installation
Each phase has different timing rules and levels of flexibility.
1. Booking Phase
An order is considered booked once:
The quotation is accepted
A deposit is received
At the point of booking:
A manufacturing window is discussed and agreed
Any critical deadlines or external constraints must be communicated at this point.
Examples include:
Other builder schedules
Planned site closures
Handover dates
Other trades depending on installation
Failure to declare fixed constraints at booking may result in delays.
2. Manufacturing Phase
Manufacturing is scheduled according to:
Batch planning
Material availability
Workshop capacity
Once manufacturing begins:
The agreed design and dimensions are considered fixed
Changes may not be possible or may incur additional costs
Manufacturing dates are planned, not guaranteed start days, and may shift slightly to optimise batch efficiency.
3. Finishing Phase
Finishing (painting, staining, oiling, etc.) is a separate production stage.
Important notes:
Drying and curing times cannot be rushed
Environmental conditions may affect duration
Finish quality takes priority over speed
Finishing timelines are estimates only.
4. Installation Phase
Installation is scheduled after manufacturing and finishing are complete.
Key points:
Installation dates are intentionally flexible
Clients should not expect a fixed installation date unless previously agreed in writing
The client will be contacted when the project is ready to be scheduled
If a fixed installation date is required:
This must be clearly stated in writing before booking
Acceptance depends on workshop capacity and may affect pricing
If no fixed date is agreed, clients are expected to wait until contacted.
Client Availability & Communication
To maintain efficient workflow:
Clients should not chase installation dates unless a critical issue arises
Regular status updates are not provided during production
Communication will occur at key milestones only
Unscheduled interruptions negatively impact workshop efficiency and delivery for all clients.
Delays & Dependencies
Delays may occur due to:
Material supply
Finishing and curing requirements
Technical adjustments
Site readiness
The workshop cannot be held responsible for delays caused by:
Undisclosed deadlines
Incomplete site preparation
Other trades
Summary
Manufacturing dates are discussed at booking
Installation dates remain flexible unless explicitly agreed in writing
Fixed deadlines must be declared upfront
Batch production requires trust in the process
This system ensures fair pricing, consistent quality, and reliable delivery across all projects.
Other information can be found here » FAQs